GTC Thomas-Warthen 500kV Transmission Line

Type: Transmission
Scope: 38.75 miles of 500kV
Location: Gibson, GA
Client: Georgia Transmission Corporation

Irby Construction Company built 38.75 miles of 500kV line for Georgia Transmission. This project crossed over several high voltage transmission lines and included installing 157 lattice steel towers on reinforced concrete pier foundations.

Irby worked on this project in conjunction with Reliable Constructors, Inc. and together we were able to complete the job six (6) months ahead of schedule.

For more information on this project, read the Georgia Transmission’s news release here.

Start Date: May 2015
Completion Date: May 2017

 

 

If you would like to request information on this project or submit a request for bid, click here. 

 