From an 11-mile, 22 kV transmission line built in 1917, Irby Construction Company has grown to become a leader in all phases of power line construction, including Extra High Voltage (EHV), transmission and distribution systems, substations, maintenance and emergency restoration.

circle_stewartirby1919

Stuart C. Irby founded Stuart C. Irby Company, which specialized in wholesale electrical supplies and electrical contracting. Irby started in the electric contracting business by erecting power lines for rural and municipal electric systems throughout the Southeast. In fact, Irby has erected more Rural Electrification Administration power lines than any other company in the United States.

circle_lineman_bw1946

Irby Construction Company was chartered as a separate organization headed by Stuart C. Irby, Jr., son of the founder. Under his leadership, the company’s growth continued, extending abroad for the first time in 1957 in Liberia, Africa.

circle_twomen1965

Irby Construction Company had successfully constructed projects in 36 states, and by 1966, it had constructed more REA projects than any other contractor in the country.

circle_heliopter1966

Irby utilized helicopters for the first time to assist in power line construction.

circle_oldtransmission1967

Irby constructed the first 765kV project in the U.S. (ultimately built over 90% of America’s total 765kV grid).

1975- 1981

Irby constructed transmission, distribution, and substations in Java, Indonesia.


1977

• Irby constructed a 112-mile, 400kV transmission line project in South Africa.

• Irby began 12 continuous years in Miami, FL building distribution.

circle_transmissionalaska1985

Irby constructed 98 miles of 345kV transmission in the environmentally sensitive Alaskan wilderness.

 

circle_oldtower1986

Irby constructed a 112-mile, 400kV transmission line project in South Africa.

 

circle_linemenapprentice1987

A leader in safety, Irby established a lineman apprenticeship program that received certification from the U.S. Department of Labor.

circle_departmentoflabor

1993

Irby received certification from the U.S. Department of Labor.

circle_belize1996

Irby completed construction of an EHV transmission line in Belize, Central America.

circle_quanta

2000

Irby Construction Company was acquired by Quanta Services, Inc. on July 10, 2000.

circle_transmission_blueorangesky

2003

Irby Construction Company completed a 192-mile 345kV transmission line for NV Energy (formerly Sierra Pacific Power Company). Majority of Right of Way on Bureau of Land Management.

circle_exxonmobile

2006

Irby Construction Company completed energized Transmission project in Chad, Africa for Exxon Mobile.

circle_transmissionpinksky

2008

Irby Construction Company was awarded LCRA (5)Year Transmission Line Construction and Maintenance Contract.

 

circle_nextera

2009

Irby Construction Company constructed a 230-mile 345kV transmission line for NextEra Energy Resources in 9 months.

 

okconstruction

2011

• Quanta Services merged Okay Construction operations into Irby.

• Irby Construiction Company was awarded 200-mile section of Central Maine Power’s Maine Power Reliability Program.

corporateheadquarters

2012

• Irby Construction Company moved into our new corporate HQ.